title |
Collaborative or adversarial production and BIM: a method for better understanding of contracting types, based on BPMN |
source |
SIGraDi 2018 [Proceedings of the 22nd Conference of the Iberoamerican Society of Digital Graphics - ISSN: 2318-6968] Brazil, São Carlos 7 - 9 November 2018, pp. 581-589 |
summary |
BIM represents a paradigm change in the production process, and its use can be facilitated or hindered by the contracting scheme. Contracting can be relational or transactional; the first refers to collaboration and the second to an adversarial environment. In literature, the different contracting schemes are presented in textual form, which is not the best format to analyze similarities and differences among them. A graphical form for comparison is proposed, using the well-known diagrams of AIA and the BPMN notation. A collaborative production process favors integration and the use of BIM, resulting in more efficiency and quality of the project. |
keywords |
BIM; BPMN; Construction contract; Integration; Production process |
series |
SIGRADI |
email |
|
full text |
file.pdf (907,700 bytes) |
references |
Content-type: text/plain
|
Eastman, C., et al. (2011)
BIM Handbook: A Guide to Building Information Modeling for Owners, Managers, Designer, Engineers and Contractors (2nd ed.)
, Hoboken: John Wiley & Sons, Inc.
|
|
|
|
Egan, J. (2002)
Accelerating change
, London: Rethinking Construction, Strategic Forum for Construction. London: Construction Industry Council
|
|
|
|
El Asmar, M., Hanna, A. S.; Loh, W. (2015)
Evaluating Integrated Project Delivery using the Project Quarterback Rating
, Journal of Construction Engineering and Management, 142.doi:10.1061/(ASCE)CO.1943-7862.0001015
|
|
|
|
Harper, C. M.,Molenaar, K.R.; Cannon, J.P. (2016)
Measuring Constructs of Relational Contracting in Construction Projects: The Owner’s Perspective
, Journal of Construction Engineering and Management, 142,1087-1098. doi:10.1061/(ASCE)CO.1943-7862.0001169
|
|
|
|
Lahdenperä, P. (2012)
Making sense of the multi-party contractual arrangements of project partnering, project alliancing and integrated project delivery
, Construction Management and Economics, 30, 57-79.doi:10.1080/01446193.2011.648947
|
|
|
|
Matthews, O.,Howell, G.A. (2005)
Integrated Project Delivery an Example of Relational Contracting
, Lean Construction Journal, 2
|
|
|
|
Miettinen, R., Paavola, S. (2014)
Beyond the BIM utopia: approaches to the development and implementation of building information modeling
, Automation in Construction, 43, 84–91.https://doi.org/10.1016/j.autcon.2014.03.009
|
|
|
|
Molenaar, K.,Sobin, N. (2009)
Sustainable, High Performance Projects and Project Delivery Methods: A State-of-Practice Report
, Vancouver, WA: CharlesPankow Foundation
|
|
|
|
Mosey, D. (2009)
Early Contractor Involvement in Building Procurement: Contracts, Partnering and Project Management
, Oxford: John Wiley & Sons, Ltd.
|
|
|
|
Nam,C. H., Tatum,C. B. (1992)
Noncontractual Methods of Integration on ConstructionProjects
, Journal of Construction Engineering and Management, 118, 385-398
|
|
|
|
Rahman, M. M.,Kumaraswamy, M.M. (2005)
Relational Selection for Collaborative Working Arrangements
, Journal of Construction Engineering and Management, 131.doi:10.1061/(ASCE)0733-9364(2005)131:10(1087)
|
|
|
|
Scheepbouwer, E., Humphries, A. B. (2011)
Transition in Adopting Project Delivery Method with Early Contractor Involvement
, Journal of the Transportation Research Board, 2228,44-50. doi:10.3141/2228-06
|
|
|
|
last changed |
2021/03/28 19:59 |
|